Application field

PhilFresh meats corporation broiler production project(Ⅱ )

Back to list

Ⅰ 、Physical features

The slope in and around the Project Area is generally flat with an average  elevation of 200m above mean sea level. The area is mostly planted with  pineapple, corn and cassava. 

The area is bounded by two rivers, Cagayan de Oro River to the north and  west, and Tumalaong River to the east. 


Ⅱ、Geology and hydrogeology

Baungon is generally underlain by Pliocene to Quaternary deposits as a  result of volcanic activities in the past. These volcanic materials may have  originated from active and inactive volcanic belt from Camiguin volcanic  complex down south to Mt. Parker in South Cotabato. Recharge of  groundwater to the Cagayan de Oro Water District wells located along the  Cagayan de Oro River banks are said to have originated from these  pyroclastic deposits. Fig. 5 gives the geology of Baungon area.

Fig. 5. Geology of Baungon, Bukidnon 

2.png

Adapted from Draft Master Plan Final Report - Formulation of an Integrated River Basin Management and  Development Master Plan, Cagayan de Oro River Basin. The Project Site is located in red circle.


Ⅲ、Water requirement and supply

The projected daily water requirement for the Project is about 50,000 Liters  per day, equivalent to 0.58 liters/sec or 2.08 cubic meters/hour. This figure  is for the broilers, farm personnel and general water consumption.  

The per capita water requirement figures can be used to determine how  much total water requirement daily is needed for the project. By multiplying  these figures according to the number of chicken, personnel and other  usage, total daily water requirement can be determined. Actual water  requirement was furnished by PhilFresh.

Water is available in the area. However, because the quantity of water  present in the area is not yet certain, this groundwater investigation was  conducted.
Table 2. Daily Water Requirement

Daily Water Requirement of PhilFresh Meats Broiler Project

1.Supply

1 Groundwater Well Well drilling may be considered as primary water supply source for the  project. Since there is no water well drilled in the area and the vicinity of  the Project Area, no reference can be established as to whether there is  groundwater source in the area or not, and if there is, how much will be  the discharge rate.

To answer the above question, seven (7) vertical electrical soundings, or  georesistivity (apparent resistivity), were measured within the Project Area  as shown in Figure 6. The results of the VES survey were given in Annex 1.

After the georesistivity survey, the raw field data were analyzed and  interpreted utilizing a software specifically for the interpretation of the  georesistivity field data.

We are looking at low resistivity values from about 10 to 100 ohm.m where  water-bearing formation may be drilled to extract groundwater. However,  the true discharge rate or flow rate of the well can only be determined after  drilling and pump testing of the well.

From the interpretation, the true resistivity and thickness of the various  lithologic (rock formation) in the area were estimated, and this are given  in Annex 2.

There are two potential water well drill sites identified in the area and this  are shown in Figure 7. The first recommended site is where the VES PFM-1  is located. PFM-1 indicates a low resistivity of 7.31 to 69.6 ohm.m, from  5.7m to 120m or an equivalent thickness of 114.43m. The other  recommended site is where VES PFM-3 is located. PFM-3 has an indicated  low resistivity value of 22.9 ohm.m at a depth from 23.3m up to infinity,  meaning the thickness of this potential water-bearing formation may  extend below 120m.

There are two more sites with low resistivity values but of lesser thickness  than the other two recommended sites. These are PFM-2 with 27m  thickness at depth from 50m to 77m, and PFM-6 with 25m thickness at  depth from 7m to 32m. These two locations may be drilled as emergency  source in the event sites 1 and 2 will encounter future problem like  shutdown for maintenance, etc. 

Fig. 6 Project Area Showing VES Point

3.png

Fig. 7 Recommended Sites for Drilling

4.png

2 Rivers 

The Project Site is bounded by two rivers which are the Cagayan de Oro  River and the Tumalaong River. If these rivers will be considered there will  be a very big problem on right of way issue plus the fact that the quality of  river water is questionable for use as source for the broiler project. These  sources will not be considered for this present study.

3 Rainwater 

The Project area is blessed with a steady rainfall all throughout the year.  Although there is rain in all months of the year, there will be times when  there is no rain in several days (see Figure 3). If rainwater will be  considered as a source for drinking water for the stocks, provision for  sufficient storage coupled with pumping if the storage will be located at  ground or underground level, should be planned ahead.

The amount of rainfall for Baungon (this applies to the Project area) is given  in Table 1, Section 4.0.

As a guide for the utilization of rainwater as an alternative source for broiler  stock drinking water, Table 3 will guide the proponent in planning for the  roof catchment and sizing of storage.

From Table 2 in Section 7.1, let us maximize the water requirement by  assuming that the per capita requirement for each mature broiler chicken  is 100mL/day. The washing/utilities and farm personnel requirement 1,200 Liters per day.

Daily Water Requirement : 50,000 L/day Provision for storage : 50,000 Liters of Storage 

Table 3. Amount of Daily Rainfall and Area of Roof Catchment for 50,000 L/day

5.png

To determine the area of roof catchment needed to capture and store  50,000 Liters of rain daily, assuming that this figure will be stored 100%,  then from Table 3, refer to the smallest daily rainfall occurrence and use  this as reference to size the roof catchment area. Since the month of  March/April has the smallest rainfall occurrence, for conservative estimate,  we will use this as reference in sizing the roof catchment; in the event when  the rain becomes more pronounced then the 50,000 Liters storage will be  filled much faster.

Therefore we need to provide at least 108,000 square meters of roof  surface to capture the rainfall in 24 hours that can be stored for  consumption.

The advantage of utilizing rainwater is that it is fresh and very little  treatment is necessary to make it suitable for any intended purpose. And  most of all it is available anywhere where it is needed. Just provide the roof  catchment and the storage/pumping facilities, and the water is there.


Ⅳ、Conclusion and recommendation

There are two recommended sites for well drilling in the area, site 1 (PFM- 1) which can drilled to 120m and site 2 which can be drilled to 120m and  deeper. Additionally two sites have the potentially for shallow well drilling  although the potential aquifer that can be tapped is less than 30m.

The quality of water in the area is fresh owing to its elevated location at  200m above sea level average.

River sources are quite far from the project and there may be problems on  right of way even if this source will be considered. From verbal accounts  springs were flowing in the area but now are long gone.

Rainwater is also a potential source of water for the project but there should  be provision for enough storage to store the desired volume of rainwater.

The total water requirement for the project is 50,000L/day which is  equivalent to 0.58 liters/sec or 2.08 cubic meters/hour. Therefore a well  which can yield 1 L/sec or 3.6 cubic meters/hour will be more than enough for the project.


leave comments