1. Test site background introduction:
Since the local climate is the most changeable, soil saline-alkalization is too extreme, resulted there is less the naturalvegetation scarce in the whole river.which also leads to the river dam and serious soil erosion, and the local land mainly in the soft soil. There are many different sizes of stones and soil slide frequently from the reality site. Except the soft clay and reinforced materials which is used infrastructure layout before in the plane, surrounded by reinforced and rigid fixation of soft soil engineering materials. The layout is mainly in the form of horizontal and surface.
2. Purposes of project implementation
1.To understand the underlying structure of the whole plane, to facilitate the selection of late mining equipment and work plan formulation.
2.)Defined the location of the rock layer cracks predicted by experts , which provides
more valuable information for the repair project.
Data collection of basic parameters for Borehole testing | |||
Items | Hole Number | Descriptions | Remarks |
A |
Northwest, deep 30m | 1. The 4 hole depth is completed at the beginning of the project, and the specific test depth may be different due to environmental changes. 2. Position refer as the center of the test plane as the coordinate,which only for explaining the approximate position relationship between the 4 holes. | |
4 Holes Basic parameter |
B |
Southwest, deep 30m | |
C | Northeast, deep 30m | ||
D | Southeast, deep 30m | ||
Cable layouts | Test details | Remarks | |
B-D | Hole depth 30m. spacing | 1. The electrodes and cables in the test | |
T171002004 | 23.5m | are mainly through WiringBox | |
A-C | Hole depth 30m. spacing | (Geomative) 20 channel. | |
T171003001 | 23.5m | 2.The electrode spacing is 1m. | |
Test between | B-C T171003002 T171003003 |
Hole depth 30m. spacing 28.5m | With 30 take-outs per cable. 3.The test depth of A-B hole is complicated because of the complicated |
A-D | Hole depth 30m. spacing | environment. It's only down to 28m.。 | |
T171003004 | 28.3m | 4.All test procedures have a length of 0.5 | |
C-D T171004001 | Hole depth 30m. spacing 17.1m | reinforcement at the first take- outs. 5.The D hole is the breakthrough of the whole metal. | |
A-B | Hole depth 28m. spacing | ||
T171005001 | 16.8m |